NEW QUESTION 27
Which is typically used in agile when estimating detailed requirements during sprint planning?
- A. Trading
- B. T-shirt sizing
- C. Rationalism
- D. Visioning
Answer: C
NEW QUESTION 28
Which process can take place during a release review workshop?
- A. Controlling a stage
- B. Directing a project
- C. Managing product delivery
- D. Managing a stage boundary
Answer: C
NEW QUESTION 29
Which statement describes the Kanban approach?
- A. It is an iterative timeboxed approach that helps teams generate value
- B. It was originally focused in creating new companies and is now used to speed up product delivery
- C. It is used to make system improvements using visualization and by controlling work in progress
- D. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
Answer: C
NEW QUESTION 30
What is an epic?
- A. The set of products handed over to the users
- B. A high-level user story that is quite broad or vague
- C. A prioritized list of requirements to be delivered in a sprint
- D. A detailed user story with high business value
Answer: B
NEW QUESTION 31
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
- A. It displays the progress rate to everyone using burn-down charts
- B. It seeks out feedback collaboratively from project stakeholders
- C. It empowers the project management team at the delivery level
- D. It uses the most effective channel to communicate information
Answer: B
NEW QUESTION 32
In Scrum, what answers the question 'what can be done this sprint?'
- A. Sprint review
- B. Daily scrum
- C. Increment
- D. Sprint planning
Answer: B
NEW QUESTION 33
Which is a purpose of the 'controlling stage' process?
- A. To establish whether the project is complete
- B. To draft the plan for the next stage's work
- C. To report stage progress to the project board
- D. To execute and deliver the project product
Answer: C
Explanation:
Reference:
%20remains%20within%20tolerance.&text=Risks%20and%20issues%20are%20kept%20under%20control
NEW QUESTION 34
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
- A. Defining non-functional requirements before functional requirements
- B. Combining functional and non-functional requirements
- C. Differentiating functional from non-functional requirements
- D. Creating non-functional requirements with user stories
Answer: C
NEW QUESTION 35
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
- A. Typical
- B. Preferable
- C. Effective
Answer: C
NEW QUESTION 36
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?
- A. It uses experimentation to expand requirements
- B. It ensures that there are no surprises
- C. It uses learning to help improve products
- D. It allows people to provide cover for one another
Answer: C
NEW QUESTION 37
How should product-based planning be used as part of PRINCE2 Agile?
- A. To plan by focusing on the features required
- B. To track progress against the team plan
- C. To enable team planning to be predictive
- D. To create the project plan using empiricism
Answer: A
NEW QUESTION 38
Which is a benefit of the Lean Startup approach to releasing a product?
- A. It enables the release plans to be synchronized with the PRINCE2 plans
- B. It provide a technique to reduce the testing of a product before release
- C. It reduces the number of people needed to manage a release of a product
- D. It provides quick feedback that can be responded to at the earliest opportunity
Answer: A
NEW QUESTION 39
In which area is Agile strongest when blending with PRINCE2?
- A. Project direction
- B. Product management
- C. Project management
- D. Product delivery
Answer: D
NEW QUESTION 40
What needs to happen when new detailed requirements are added to a timebox?
- A. The delivery milestones should be reviewed and re-planned
- B. Formal change control should be applied
- C. More people should be added to the delivery team
- D. Requirements of a similar level of effort should be removed
Answer: D
NEW QUESTION 41
Which statement about the 'keep teams stable' target is CORRECT?
- A. It results in the early delivery of a minimum viable product
- B. It is the primary reason why the tolerance for cost is set to zero
- C. It applies primarily to the long term, such as a project or a program
- D. It prevents compromising the overall quality level of the product
Answer: B
NEW QUESTION 42
How does the change theme regard change in PRINCE2 Agile?
- A. As a necessity
- B. As disruptive
- C. As inevitable
- D. As something to be avoided
Answer: C
NEW QUESTION 43
Which statement about the 'protect the level of quality' target is CORRECT?
- A. It delivers the early realization of benefits
- B. It gives confidence on the progress of the project
- C. It is achieved by using the same team members
- D. It is achieved by allowing enough time for testing
Answer: A
Explanation:
Reference:
%20level%20is%20met
NEW QUESTION 44
How is the 'tailor to suit the project' principle applied in an agile context?
- A. By emphasizing tolerances on what is being delivered
- B. By flexing what is produced to stay in control and deliver value
- C. By fitting releases into planned management stages
- D. By using the Agilometer to assess the project environment
Answer: B
NEW QUESTION 45
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- A. To fail fast, if you are going to fail
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To use empiricism, based on knowledge that comes from experience
Answer: D
NEW QUESTION 46
Why are team working agreement produced?
- A. To evolve the effectiveness and behaviors of the self-organizing team by agreeing values
- B. To ensure that the delivery team members comply with company policy
- C. To create structure so that the team manager can assess individual performance
- D. To make the team rules visible to the project manager for monitoring purposes
Answer: A
Explanation:
Reference https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_126&showNav=true&expandNav=true
NEW QUESTION 47
......
Updated Verified Pass PRINCE2-Agile-Foundation Exam - Real Questions & Answers: https://www.itpassleader.com/PRINCE2/PRINCE2-Agile-Foundation-dumps-pass-exam.html
Best Way To Study For PRINCE2 PRINCE2-Agile-Foundation Exam Brilliant PRINCE2-Agile-Foundation Exam Questions PDF: https://drive.google.com/open?id=1PEVpCsjhKKXv9GgWRTh3CWDdlIc0l_Be